Ohio Supreme Court Approves AEP's 2012 Fee Pricing Structure

google.com

The Ohio Supreme Court has upheld a pricing structure for fees that competitors must pay American Electric Power as the utility transitions to a competitive market.

The court's Thursday ruling sided with a 2012 decision by the Public Utilities Commission of Ohio to set the fee at $188.88 per megawatt-day.

The decision also upholds the requirement that AEP charge suppliers a lower market-based price.

AEP had objected to the $188.88 rate, arguing that it was too low to recover its actual costs to provide capacity. The utility wanted to charge suppliers $355 per megawatt-day.

The Ohio Consumers Counsel, which represents utility consumers, had challenged PUCO's authority to approve the capacity charge and to defer the recovery of capacity costs.

The court rejected both challenges.

The AP is one of the largest and most trusted sources of independent newsgathering, supplying a steady stream of news to its members, international subscribers and commercial customers.